Construction Timeline

Phase 1
May–August 2015

  • Administrative offices move to Parish House at St. Ann’s & the Holy Trinity Church, located at 157 Montague Street (including Finance, Admissions, Development, College Office, Assistant Head of School)
  • Rotunda space open at 53 Clinton Street for classes, rehearsals, gatherings, performances
  • High School Office moves up to 3rd Floor; work begins for new Bosworth Building kitchen
  • New restrooms built on 1st and 3rd floor of Bosworth

Academic Year 2015–2016

  • 122 Pierrepont under construction for 2015-16
  • 124 Admin offices replaced with classrooms
  • Limited work in the Bosworth Building (primarily construction of new kitchen)

Phase 2
Summer 2016

  • Renovation of 124 Pierrepont for art studios and classrooms
  • Renovation of Undercroft through 3rd floor of Bosworth Building